| Edif 10 Pisos Balcones Hormigon |
MATERIALES
| Material | ID Tarea | Rendimiento | Manos | Litros | Cantidad | Costo Unitario | Costo Total |
|---|---|---|---|---|---|---|---|
| sikadur 32 gel | 0 | 0 | 0 | 5 | $1200 | $6000 | |
| Monotop 615 | 0 | 0 | 10 | $1100 | $11000 | ||
| Monotop 620 | 0 | 0 | 3 | $1900 | $5700 | ||
| Sika Top Armatec 108 | 0 | 0 | 1 | $2510 | $2510 | ||
| Elastocolor | 8 | 3 | 20 | 10 (500 M2) | $6500 | $65000 |
| TOTAL MATERIALES | $90210 |
OPERARIOS
| Categoria Operario | ID Tarea | Cantidad | Jornales | Comentario | Total |
|---|---|---|---|---|---|
| Oficial | 4 | 14 | 1 - Reparacion hormigon | $140942.17 | |
| Peon | 0 | 0 | 0 | $0 | |
| Oficial | 4 | 1.2 | 2 - Empapelar marcos alu ventanas y pasa balcones balcones vidrio | $17514.33 | |
| Oficial | 4 | 5 | 3 - Pintura hormigón 3 manos y limpieza vidrios | $54156.97 | |
| Oficial | 4 | 5 | 4 - Mamposteria | $54156.97 | |
| ALT1 | 2 | 24 | $31200 | ||
| ALT2 | 2 | 24 | $17760 | ||
| Oficial | 2 | 4 | 5 - Hidrolavado | $25228.57 |
| MANO DE OBRA | $319548.79 | ||
| TOTAL CON UTILIDAD | $750939.6565 |
| JORNALES TRANSCURRIDOS | 0 |
REPLANTEO DE TAREAS
| Tarea | ID Tarea | Dias | M2 | $/M2 | Costo Total | Jornales x Dias |
|---|---|---|---|---|---|---|
| 1 - Reparacion hormigon | 1 | 14 | 0 | 183029 | ||
| 2 - Empapelar marcos alu ventanas y pasa balcones balcones vidrio | 2 | 1.2 | 0 | 15688.2 | ||
| 3 - Pintura hormigón y limpieza vidrios | 3 | 5 | 0 | 65367.5 | ||
| 4 - Mamposteria | 4 | 5 | 0 | 65367.5 | ||
| 5 - Implantacion e hidrolavado | 5 | 0 | 0 |
| TOTAL JORNALES X DIAS | $329452.2 | ||||
| TOTAL TAREAS | $0 | ||||
| DIAS TOTALES | 25.2 |
EXTRAS
| Extra | Costo |
|---|
| TOTAL EXTRAS | $0 |
TOTALES
| UTILIDAD / DIA | $17118.69 | USD 454.2 |
| UTILIDAD / MAT+M.O. | 105 % | |
| MANO OBRA | $319548.79 | USD 8478.34 |
| MATERIALES | $90210 | USD 2393.47 |
| SYSO | $8000 | USD 212.26 |
| RESP CIVIL | $0 | USD 0 |
| IMM | $0 | USD 0 |
| INC OBRA | $5000 | USD 132.66 |
| UTILIDAD | $431390.87 (135 %) | USD 11445.76(135 %) |
| SUBTOTAL | $854149.66 | USD 22662.5 |
| BPS | $172425.3696 | USD 4574.83 |
| IRPF | $0 | USD 0 |
| IVA | $187912.93 | USD4985.750331653 |
FINANCIACION SELECCIONADA:
| Plan de Pagos | Valor Cuota | IVA Incluido | USD | Interes 0 % | USD |
|---|---|---|---|---|---|
| 50 % Inicio | $521031.3 | $635658.19 | USD 16865.43 | ||
| 0 cuotas | $INF | $INF | USD INF | $NAN | USD NAN |
OTRAS FINANCIACIONES:
| Plan de Pagos | Valor Cuota | IVA Incluido | USD | C/Recargo | USD |
|---|---|---|---|---|---|
| 50 % Inicio | $521031 | $114626.89 | USD 3041.31 | ||
| 3 | $173677.1 | $38208.96 | USD 1013.77 | ||
| 6 | $86838.55 | $19104.48 | USD 506.88 | $19677.61 | USD 522.09 |
| 10 | $52103.13 | $11462.69 | USD 304.13 | $12265.08 | USD 325.42 |
| 12 | $43419.27 | $9552.24 | USD 253.44 | $10316.42 | USD 273.72 |
| 18 | $28946.18 | $6368.16 | USD 168.96 | $6877.61 | USD 182.48 |
| 24 | $21709.64 | $4776.12 | USD 126.72 | $5158.21 | USD 136.86 |
| 36 | $14473.09 | $3184.08 | USD 84.48 | $3438.81 | USD 91.24 |
COMENTARIOS
NO HAY ARCHIVOS ADJUNTOS
PRESUPUESTOS HIJOS

PRESUPUESTO ALT1202
| Cielo Rasos Madera |
MATERIALES
| Material | ID Tarea | Rendimiento | Manos | Litros | Cantidad | Costo Unitario | Costo Total |
|---|---|---|---|---|---|---|---|
| lijas | 0 | 0 | 1 (500 M2) | $1000 | $1000 | ||
| Barniz | 8 | 2 | 4 | 19 (300 M2) | $3000 | $57000 |
| TOTAL MATERIALES | $58000 |
OPERARIOS
| Categoria Operario | ID Tarea | Cantidad | Jornales | Comentario | Total |
|---|---|---|---|---|---|
| MedioOf | 2 | 4 | Lijado de Cielo Rasos Madera | $21017.7 | |
| Oficial | 2 | 5 | $31339.1 |
| MANO DE OBRA | $46126.81 | ||
| TOTAL CON UTILIDAD | $108398.0035 |
| JORNALES TRANSCURRIDOS | 0 |
REPLANTEO DE TAREAS
| Tarea | ID Tarea | Dias | M2 | $/M2 | Costo Total | Jornales x Dias |
|---|
| TOTAL JORNALES X DIAS | $0 | ||||
| TOTAL TAREAS | $0 | ||||
| DIAS TOTALES | 0 |
EXTRAS
| Extra | Costo |
|---|
| TOTAL EXTRAS | $0 |
TOTALES
| UTILIDAD / DIA | $INF | USD INF |
| UTILIDAD / MAT+M.O. | 60 % | |
| MANO OBRA | $46126.81 | USD 1223.85 |
| MATERIALES | $58000 | USD 1538.87 |
| SYSO | $0 | USD 0 |
| RESP CIVIL | $0 | USD 0 |
| IMM | $0 | USD 0 |
| INC OBRA | $0 | USD 0 |
| UTILIDAD | $62271.19 (135 %) | USD 1652.19(135 %) |
| SUBTOTAL | $166398 | USD 4414.91 |
| BPS | $31514.08 | USD 836.14 |
| IRPF | $0 | USD 0 |
| IVA | $0 | USD0 |
| Plan de Pagos | Valor Cuota | IVA Incluido | USD | C/Recargo | USD |
|---|---|---|---|---|---|
| 0 % Inicio | $0 | $0 | USD 0 | ||
| 3 | $55466 | $55466 | USD 1471.64 | ||
| 6 | $27733 | $27733 | USD 735.82 | $28564.99 | USD 757.89 |
| 10 | $16639.8 | $16639.8 | USD 441.49 | $17804.59 | USD 472.4 |
| 12 | $13866.5 | $13866.5 | USD 367.91 | $14975.82 | USD 397.34 |
| 18 | $9244.33 | $9244.33 | USD 245.27 | $9983.88 | USD 264.89 |
| 24 | $6933.25 | $6933.25 | USD 183.95 | $7487.91 | USD 198.67 |
| 36 | $4622.17 | $4622.17 | USD 122.64 | $4991.94 | USD 132.45 |
COMENTARIOS
NO HAY ARCHIVOS ADJUNTOS
PRESUPUESTO ALT1203
| Edif 10 Pisos Balcones Hormigon |
MATERIALES
| Material | ID Tarea | Rendimiento | Manos | Litros | Cantidad | Costo Unitario | Costo Total |
|---|---|---|---|---|---|---|---|
| sikadur 32 gel | 0 | 0 | 0 | 5 (300 M2) | $1200 | $6000 | |
| Monotop 615 | 0 | 0 | 10 (300 M2) | $1100 | $11000 | ||
| Monotop 620 | 0 | 0 | 3 (300 M2) | $1900 | $5700 | ||
| Sika Top Armatec 108 | 0 | 0 | 1 (300 M2) | $2510 | $2510 | ||
| Elastocolor | 8 | 3 | 20 | 10 (500 M2) | $6500 | $65000 |
| TOTAL MATERIALES | $90210 |
OPERARIOS
| Categoria Operario | ID Tarea | Cantidad | Jornales | Comentario | Total |
|---|---|---|---|---|---|
| Oficial | 4 | 14 | 1 - Reparacion hormigon | $140942.17 | |
| Peon | 0 | 0 | 0 | $0 | |
| Oficial | 4 | 1.2 | 2 - Empapelar marcos alu ventanas y pasa balcones balcones vidrio | $17514.33 | |
| Oficial | 4 | 5 | 3 - Pintura hormigón 3 manos y limpieza vidrios | $54156.97 | |
| Oficial | 4 | 10 | 4 - Mamposteria | $102370.97 | |
| ALT1 | 2 | 29 | $37700 | ||
| ALT2 | 2 | 24 | $17760 | ||
| Oficial | 2 | 4 | 5 - Hidrolavado | $25228.57 |
| MANO DE OBRA | $370734.79 | ||
| TOTAL CON UTILIDAD | $815616.538 |
| JORNALES TRANSCURRIDOS | 0 |
REPLANTEO DE TAREAS
| Tarea | ID Tarea | Dias | M2 | $/M2 | Costo Total | Jornales x Dias |
|---|---|---|---|---|---|---|
| 1 - Reparacion hormigon | 1 | 14 | 0 | 183029 | ||
| 2 - Empapelar marcos alu ventanas y pasa balcones balcones vidrio | 2 | 1.2 | 0 | 15688.2 | ||
| 3 - Pintura hormigón y limpieza vidrios | 3 | 5 | 0 | 65367.5 | ||
| 4 - Mamposteria | 4 | 10 | 0 | 130735 | ||
| 5 - Implantacion e hidrolavado | 5 | 0 | 0 |
| TOTAL JORNALES X DIAS | $394819.7 | ||||
| TOTAL TAREAS | $0 | ||||
| DIAS TOTALES | 30.2 |
EXTRAS
| Extra | Costo |
|---|
| TOTAL EXTRAS | $0 |
TOTALES
| UTILIDAD / DIA | $14731.18 | USD 390.85 |
| UTILIDAD / MAT+M.O. | 97 % | |
| MANO OBRA | $370734.79 | USD 9836.42 |
| MATERIALES | $90210 | USD 2393.47 |
| SYSO | $8000 | USD 212.26 |
| RESP CIVIL | $0 | USD 0 |
| IMM | $0 | USD 0 |
| INC OBRA | $5000 | USD 132.66 |
| UTILIDAD | $444881.75 (120 %) | USD 11803.71(120 %) |
| SUBTOTAL | $918826.54 | USD 24378.52 |
| BPS | $204121.2096 | USD 5415.79 |
| IRPF | $0 | USD 0 |
| IVA | $202141.84 | USD5363.2751392942 |
| Plan de Pagos | Valor Cuota | IVA Incluido | USD | C/Recargo | USD |
|---|---|---|---|---|---|
| 50 % Inicio | $560484 | $123306.52 | USD 3271.6 | ||
| 3 | $186828.06 | $41102.17 | USD 1090.53 | ||
| 6 | $93414.03 | $20551.09 | USD 545.27 | $21167.62 | USD 561.62 |
| 10 | $56048.42 | $12330.65 | USD 327.16 | $13193.8 | USD 350.06 |
| 12 | $46707.02 | $10275.54 | USD 272.63 | $11097.58 | USD 294.44 |
| 18 | $31138.01 | $6850.36 | USD 181.76 | $7398.39 | USD 196.3 |
| 24 | $23353.51 | $5137.77 | USD 136.32 | $5548.79 | USD 147.22 |
| 36 | $15569.01 | $3425.18 | USD 90.88 | $3699.19 | USD 98.15 |
COMENTARIOS
NO HAY ARCHIVOS ADJUNTOS
| ID | # Operario | Nombre Operario | Fecha Asignacion | Asignado Por | Horas | Categoria |
|---|
| ID | Gasto | Concepto | Registrado Por |
|---|
TOTAL: $0
| ID | Pago | Concepto | Registrado Por |
|---|
TOTAL: $0
SELECCION MONEDA PDF/EXCEL:
|
Montevideo, 11 de abril de 2026 PRESUPUESTO ID: ALT1201 Estimado/s señor/es: Beatriz Objeto: [OBJETO] Edificio ubicado en: Rbla Mahatma Gandi 585 Por medio de la presente le hago llegar el presupuesto por suministro de mano de obra y herramientas necesarios para llevar a cabo dicha obra, PROOBRA, Martín Porcires con numero de rut 217387910015, BPS 6444676 es la empresa contratada que llevará a cabo la tarea descrita y se responsabiliza por la correcta aplicación de los materiales. El siguiente presupuesto incluye: - Mano de obra. - Aportes BPS. - Seguro de responsabilidad civil, BSE. - Inscripción de obra ante entes públicos. - Permisos ante IMM. - SYSO Seguridad y Salud ocupacional. - Suministro de herramientas. - Materiales. - Protección de pisos y equipos etc. - Limpieza fin de obra. - Cierre de obra ante todos los entes. ____________________________________________________________ COTIZACIÓN: 1) Edif 10 Pisos Balcones Hormigon [COTIZACION] Precio...............................................$
2) Cielo Rasos Madera [COTIZACION] Precio...............................................$
3) Edif 10 Pisos Balcones Hormigon [COTIZACION] Precio...............................................$
TOTAL..............................................$
Nota: Los precios incluyen materiales. ____________________________________________________________ COTIZACIÓN: Aportes al BPS, BSE. El monto máximo de aporte al Banco de Previsión Social (BPS) por parte de la parte contratante respecto de esta obra, y que de superarse será de cargo del Contratista, alcanza a la suma de 1) Precio...............................................$
2) Precio...............................................$
3) Precio...............................................$
TOTAL..................................................$
Nota: serán presentadas ante la administración las boletas y nominas de obra para su pago. ____________________________________________________________ COTIZACIÓN: Inscripción de obra • Inscripción ante entes públicos: BPS/MTSS/FOCER • Clausura ante entes correspondientes • Clausura ante BPS Será necesario presentar para inscribir la obra ante BPS presupuesto firmado por ambas partes y factura de tributos municipales o contribución inmobiliaria. Minuta notarial. Precio...................................................$
____________________________________________________________ COTIZACIÓN: SYSO, plan y estudio de seguridad e higiene {SYSO} Precio...................................................$
____________________________________________________________ FORMAS DE PAGO: TASA DE INTERES.......................................................%
ENTREGA INICIAL........................................................$
CUOTAS IGUALES Y CONSECUTIVAS VALOR CUOTA.............................................................$
{FORMASPAGO} ____________________________________________________________ TOTALES. MANO DE OBRA Y MATERIALES............$
Inscripcion Obra........................................$
SYSO..........................................................$
IVA..............................................................$
SUBTOTAL................................................$
BPS.............................................................$
TOTAL.........................................................$
FORMAS DE PAGO FINANCIADO MANO DE OBRA, MATERIALES E IVA. 50 % de entrega inicial al confirmar el trabajo, $ XXXXXX. Saldo en X cuotas mensuales, iguales y consecutivas de $ XXXXXX- Nota: Consultar por otros planes de financiación. Tanto los costos de IMM como BPS no esta incluido en las cuotas, el mismo deberá ser pago con su factura del mes correspondiente. En caso de realizar los pagos a través del estado estamos afiliados a RUPE. COTIZACIÓN. Informe de avance de obra quincenal (opcional). Memoria descriptiva con registros fotográficos de cada etapa. Precio................................................$ 35.000 Inicio de obra: Después de firmar se fija fecha con un plazo de dos meses máximo para el inicio de obra. El plazo de obra: {PLAZO} Jornales: Se estiman 269.6 jornales. Operarios: El trabajo se realizara con 2 a 4 operarios. El precio es válido por 45 días. El presente presupuesto tiene valor únicamente con el contrato que lo acompaña. Garantía: Los trabajos realizados bajo este presupuesto tienen una garantía por defectos de materiales y mano de obra de 5 años desde la Recepción Definitiva de la Obra. No incluye problemas ocasionados por humedades existentes o futuras por factores externas al presente contrato. El cliente debe de proveer lugar físico, “deposito” para herramientas y materiales. Suministro de electricidad y agua. Si el edificio no cuenta con un baño de servicio, se contratara uno a cuenta del mismo. Instalación de tablero eléctrico provisional, con firma autorizada. Sobre fachada en lugar a convenir la empresa instalara cartel de obrador 1 x 1,5 m aproximado. No incluidos en el precio: o No incluye ningún material, servicio o trabajo no expresamente detallado en la presente cotización. o No incluye reparación, colocación o sustitución de objetos que se encuentren del lado exterior de fachada, balcones, terrazas o donde se realizaran los trabajos. Tales como redes de protección, plantas, muebles, ropa, adornos, cortinas, etc. Para ello se dará aviso con anticipación fechas de inicio de obra. Solicitamos en caso que hayan redes de protección etc. retirarlas para colocar las una vez finalizado la obra. No obstante deciden dejarlo tendremos el mayor cuidado posible. o No incluye tratamientos o arreglos a cerramientos de aberturas. o No incluye arreglos ni impermeabilización de pisos de balcones En caso de existir puntos de su interés que no fueron evaluados en el presente presupuesto quedamos a disposición para coordinar las visitas necesarias y poder evacuar todas las dudas. Por PROOBRA lo saluda muy atentamente. ------------------                            ------------------   Martin Porcires                                  Cliente             099 363 251                                                       |